Ashmoun General Hospital


Owner:

Ministry of Health and Housing ​

Main Contractor (Client):

Delta Urban Development

Consultant: 

CPAS - "Prof. Dr. Abdel baki & Partners"

Project Type: 

Hospitals and Health Care

Project Duration:

Start date:  17/1/2024

Expected Completion date:  25/11/2025

Location:

Ashmoun Monoufia , Egypt

Scope of Work:

Mechanical Systems:

  • Heating , Ventilation and Air conditioning systems

Challenges & Achievements:​

Hygiene Standards


Visual Gallery:


Image 1 Image 2 Image 3


Damnhur University Hospital & Faculty of Medicine


Owner:

 Ministry of Higher Education and Scientific Research

Main Contractor (Client):

Delta Urban Development

Consultant: 

TOP ENGINEERING (Dr. Mohamed Abou-Elfotouh)


Project Type: 

Hospitals and Health Care

Project Duration: 

Start date: 19/11/2024

Expected Completion date: 19/12/2025

Location: 

 Damanhour, Behiera, Egypt

Scope of Work:


Mechanical Systems:

  • Heating , Ventilation and Air conditioning systems


Electrical  Systems:

  • Low Voltage Systems (Lighting, Power, Cabling, Panels,  … etc )
  • Low Current Systems (Nurse Call System, Master Clock system , Access Control System, Public Address system , Queuing System,  ..etc)


Challenges & Achievements:

  • Hygiene Standards

Visual Gallery:


Image 1 Image 2 Image 3


El- Kada Hospital


Client

Armed Forces Engineering Authority, Egypt

Main Contractor: 

GAMA Construction

Consultant: 

MESD

Project Type: 

Hospitals & Health Care

Project Duration: 

Start date: 24-7-2019

Completion date: 30-6-2020

Location: 

Egypt’s New Administrative Capital

Scope of Work:

 Electromechanical Works (From Scratch):-


Mechanical Systems:

  • Fire Fighting Systems
  • Infrastructure for electrometrical systems


Key Features:

  • Hygiene standards

  • Visual Gallery:


Image 1 Image 2 Image 3


Suez Medical Complex


Client

Ministry of Health

Main Contractor: 

Al-Marasem


Consultant: 

ECG: ( Engineering Consulting Group )


Project Type: 

Hospital & Health care.


Project Duration: 

Start date:  15/10/2021

Completion date:  15/10/2023


Location: 

Suez, Egypt


Scope of Work:

Turnkey Project including Civil, Mechanical and Electrical Works:


Civil Works:


Mechanical Works:

  • Fire Fighting Systems
  • Heating, Ventilation, and Air Conditioning (HVAC Systems).

Key Features: 

  • High international standards and specifications

Visual Gallery:

Image 1 Image 2 Image 3